For this project we were contracted to design a curbless walk-in shower conversion from an old tub & shower layout. The goal was to create a safe place for our client to shower with no physical obstructions.
We completed the demo in one day and framed the floor to allow for a Schluter offset drain pan to be installed flush with the bathroom floor. Additional framing supports were installed to allow for grab bars and future seating installations.
Supply chain issues due to the COVID pandemic forced us to schedule the project for 6 weeks from start to finish. We completed on time and on budget.
Only a few changes were made from the original design. It was important to provide additional storage over the toilet and replace some electrical light fixtures and accessories to better match the aesthetic.
Shower fixtures are Riobel Zendo with full thermostatic control and three way setting to the shower head, hand shower on the bar, or both.
A custom niche was installed along with a grab bar for safety and the seating was replaced with a shower stool.
Baseboards were fabricated from the same terrazzo floor tile to complete a seamless transition.
Project Budget $10,533.88
Design $199.99
Build Material $ 5,431.41
Build Labour $ 4,505.16
Change Orders $ 397.32
This Etobicoke Ensuite needed an oversized neo-angle shower to complete the custom remodel. The design was based on our client's wish list to include dual shower heads, controls and niches.
Our client started the remodel with another contractor but did not feel the deadline for paint and shower glass could be met so they contracted us to bring the project back in line. Glass was templated and they
Once the project was approved, we started the demo on Monday morning. The Schluter Neo-Angle pan was oversized and waterproofed from ceiling to curb, including the two custom sized niches. The build took 7 days to complete from start to finish.
Project Budget $11,476.20
Design $199.99
Build Material $ 5,333.07
Build Labour $ 5,917.14